| Disaster Management – Flood Project Chinnambavi, Mahabubnagar District
|
|
| The Flood housing project for the 56 families is progressing at a rapid pace and heading for a completion by December 2010. The current status of housing project is as under:
|
|
| S.NO. |
Structure Level |
Status |
| 1 |
Basement level |
01 |
| 2 |
Roof casting |
55 |
| Total |
56 |
|
|
| Plastering work for the roof casted houses is progressing at a rapid pace and construction of toilets is also under way. The civil works for the proposed safe drinking water plant is currently undertaken and would be completed by November-end. |
|
| Under our School improvement program, civil works have commenced for the construction of Kitchen Shed and improving toilets, and overhead tank water facility at Govt. High School Peddadagada (4 Kms. off Chinnambavi flood site). All constructions will completed by end of November 2010.
|
|
 |
| |
|
|
|
|
|
|
|